Level9 EW-01 · Your page For the COO · you brought the question and you sign it · ELT meeting Thursday
Example · the East-West company from We've Done It Backwards

For the COO · read before Thursday

You're signing for one team. Before Thursday, decide who runs it.

The room settled whether to combine East and West support. It didn't settle who leads the combined team, or who pays for the switch. Both of those land on you, and everyone at the table knows it.

What the room recommends

Combine into one support organization, keep both offices open through the switch, and don't cut over until a failover test has passed.

How the six seats voted

2 for · 1 no block · 1 conditional · 2 against

Deals to close

4

Before anyone sits down

Risks you own

6

Each with an early warning

Saved a year

$640k

$380k of it lands in Facilities

Cost to do it

$395k

$245k of it lands on your side

Your job Thursday

Run the room. Close two no votes. Sign.

The COO's 90 seconds

1:27 · read by an AI voice · Example · East-West

0:00

The question nobody's asked out loud

The plan removes one management layer, and all 14 roles that change are on the West side. Both support leads can do that math.

West support lead

Voted for it

For

They voted for a plan that may change their own job, and they haven't asked about it.

Your move

Talk to them before Thursday, one on one. Don't let them learn their future in the meeting.

East support lead

Conditional

Conditional

They're about to absorb West's peaks, and either run the bigger team or report to someone who does.

Your move

Tell them what "cross-trained" has to mean before they carry the load, in hours and in dates.

Your call

Name who leads the combined team, or the date you will.

HR can't tell 14 people what happens to their roles until the top role is settled. Their first move waits on yours.

Latest date

Day 14, when the role conversations start.Not decided

Four deals to close before Thursday

Each one sits between two teams. Close them before the meeting and the meeting only has to sign.

OperationsandFinance

Operations pays $110k and saves nothing.

The failover and phone work sits in Operations' budget, and none of the savings come back to them. That's part of why they voted no.

The deal: move the $110k into the program budget, next to the lease savings.

OperationsandWest lead

The cutover date.

West wants it fast because holds keep climbing. Operations wants proof first. Both are right.

The deal: the failover test sets the cutover date. Give West relief sooner. From day 30, East takes West's peak-hour overflow once the first group is trained.

East leadandFinance

Training slows East down first.

Every East agent in training is off the phones. East holds sit at 4:10 today and will rise while training runs.

The deal: train in waves of five, and build overtime backfill into the $135k training budget.

CMOandFinance · HR

Whose three people?

If the CMO's 8 percent holds, you need about 3 more agents, $190k a year. Nobody has said whose headcount they'd be.

The deal: they go in the combined support budget, funded from year one savings, and HR starts hiring by day 60.

Who pays, who saves

The same $640k and $395k as everyone's page, split by the team that feels it.

TeamPays onceSaves a yearWhat they'll feel
Facilities, under the CFO$150k lease break$380k leaseThe big winner
Support, yours$135k cross-training$260k management layerDrops to $70k if the CMO is right
Operations$110k failover and phones$0Pays for a plan it voted against
HRTime for 14 conversations$0Carries the hardest two weeks
Everyone$395k$640k, or $450kPays back in about 7 months, or 21 if two things slip

The savings land in Facilities. The costs land in Support and Operations. Leave it that way and the two teams paying will keep finding reasons to wait. Fix it with the first deal above.

Risks you own

Each one has an early warning, so you see it coming before it's a reopen.

RiskEarly warningOwnerWhat you do
The failover test failsThe test date slips past day 60VP OperationsHold the cutover. This one reopens the decision.
West holds get worse during the switchOver 13 minutes three days runningWest leadPause the cutover and add East overflow hours.
East holds rise while training runsOver 6 minutes on any dayEast leadSlow the training waves.
Top West agents leave when the news breaks2 resignations in the first 30 daysCHRORetention offers to the top five by day 14.
The lease exit slips past year oneNo landlord answer by day 30General CounselTell the CFO. Payback moves to about 15 months.
The CMO's 8 percent holdsThe volume check confirms itCMOHire 3 by day 60. Payback moves to about 11 months.

What the CEO will ask you

The CEO's page tells them to ask three questions. Two of them come to you.

  • To VP Operations, and then to you

    "What date can you show me failover working?"

    Have the date, or the day you'll have it. Without one the plan has no gate.

  • To the CFO, and then to you

    "What does payback look like if the lease slips and the CMO's number is right?"

    About 21 months. Say it's still worth doing, and say why.

  • To the CMO

    "Does your 8 percent change whether we do this, or only how many people we need?"

    Only how many. Be ready to say whose budget the three people sit in.

How to run the room

  1. 0 to 5

    Two sentences. The question, then the answer. The seats already made the case.

  2. 5 to 10

    HR first. Say yes to their order, and say who leads the combined team or when you'll decide.

  3. 10 to 18

    Operations. Get the test date on the record. Announce that the $110k moves to the program budget.

  4. 18 to 25

    The CMO's 8 percent. Call it a staffing question. Name who owns the hiring and by when.

  5. 25 to 30

    Sign it, or send it back pointing at the page.

  • Talk last on the plan and first on the people.
  • Close the no votes. Don't argue with them.
  • Any new topic gets an owner and a date, then you move on.

Where every seat stands

The full seat-by-seat view is on the CEO's page. This is the short version.

For CFO For West lead No block General Counsel Conditional East lead Against VP Operations Against as sequenced CHRO Pushed back after CMO

Before Thursday

Five short notes. Most of the meeting happens here.

To the West support lead

Can we grab 20 minutes before Thursday? I want to talk about your role in the combined team.

To the CFO

Can the $110k failover and phone work sit in the program budget, next to the lease savings?

To VP Operations

Bring the failover test date Thursday. I'm moving the $110k into the program budget.

To the East support lead

Plan the cross-training in waves of five, and put the backfill in the $135k.

To the CHRO

Start drafting the 14 conversations. You'll have who leads the combined team from me before day 14.

Your first 90 days

One review a week, 15 minutes, three numbers: West hold time, East hold time, and where the failover test stands.

Day 1 to 14

Name the leader. Talk to all 14 people.

You · CHRO

Day 30

East starts taking West's peak overflow

East lead

Day 30

Notices out, lease exit started

General Counsel · CFO

By day 75

Failover test passes

VP Operations

Day 90

Cutover, only if the test passed

You

Reopen if the failover test fails Reopen if West hold times rise during the switch Reopen if the lease exit slips past year one