Level9 EW-01 · Your page For the CFO · the money case is yours · ELT meeting Thursday
Example · the East-West company from We've Done It Backwards

For the CFO · read before Thursday

Your seven months is right. It rests on two things nobody has confirmed.

The room backs combining East and West support, and your cash case is why it looks easy. It assumes the West lease ends in year one and the file's customer volume is right. Neither one is checked yet.

What the room recommends

Combine into one support organization, keep both offices open through the switch, and don't cut over until a failover test has passed.

Saved a year

$640k

Lease $380k, one management layer $260k

Cost to do it

$395k

All of it spent before day 90

Pays back

~7 mo

After the switch, if nothing slips

If both slip

~21 mo

The CEO will ask you this

Your vote

For. Say what it depends on before anyone else does.

The CFO's 70 seconds

1:12 · read by an AI voice · Example · East-West

0:00

The two numbers your case rests on

Each one alone still pays back inside about a year and a half. Together they take it to almost two years.

Legalowns the answer

The West lease ends in year one.

Seven months needs the $380k lease saving from the first year. The break clause is in the lease, but nobody has called the landlord.

If it slips a year: payback moves to about 15 months.

CMOowns the answer

The file's customer volume is right.

The CMO says contacts run 8 percent higher than the file. If so, the combined team needs about 3 more agents, $190k a year.

If the CMO is right: savings drop to $450k and payback moves to about 11 months.

When the cash comes back

Cumulative cash from today. Everything is spent by the switch at day 90, so that's the low point.

+$200k $0 -$200k -$400k Now 6 mo 12 mo 18 mo 24 mo 30 mo Switch, day 90 Nothing slips: back to zero, month 10 Both slip: back to zero, month 24

Who pays, who saves

The savings land in your Facilities line. The costs land in Support and Operations.

TeamPays onceSaves a yearWhat it means for you
Facilities, yours$150k lease break$380k leaseMost of the upside lands here
Support$135k cross-training$260k management layerOnly $70k left if the CMO is right
Operations$110k failover and phones$0The COO will ask you to move this
Everyone$395k$640k, or $450kAbout 7 months, or 21 if both slip

What you'll be asked

  • From the CEO

    "What does payback look like if the lease slips and the CMO's number is right?"

    About 21 months. Say it's still worth doing, and that the lease is the one to chase first.

  • From the COO

    "Can the $110k failover and phone work sit in the program budget?"

    Say yes. It's the cheapest way to turn Operations' no, and it doesn't change the total.

  • From the COO, if the CMO is right

    "Can we fund three more agents from year one savings?"

    Yes, and payback still lands around 11 months.

Numbers you bring Thursday

The numberStatus
Payback under all four casesReady
Cash low point, $395k at day 90Ready
Cost of 3 more agents, $190k a yearReady
What breaking the lease really costsComing from Legal
The CMO's volume checkDue tomorrow

Risks to the numbers

What would move your case, and what you'd see first.

RiskYou'd see it first asWhat it does to the case
The lease exit slipsNo landlord answer by day 30Payback to about 15 months
The CMO's volume holdsThe check confirms 8 percent$190k a year more, payback about 11 months
Training backfill runs overOvertime past plan by day 45Eats into the $135k, then into savings
The failover test fails and needs reworkThe test date slips past day 60More one-time cost, and the switch moves out
West agents leave early2 resignations in 30 daysHiring and overtime before the savings start

Before Thursday

Three notes that turn your two assumptions into facts.

To General Counsel

Can you get the landlord's answer on the West lease break before Thursday? My payback depends on it.

To the CMO

Send me your volume numbers before Thursday so I can rerun the case, even if they're rough.

To the COO

I'm fine moving the $110k failover and phone work into the program budget. Put it on the page for Thursday.